VIMODRONE’S MUNICIPALITY (MILAN):
MUNICIPAL SUSTAINABLE ENERGY PLAN

Status

The City of Vimodrone, located in the north - east of Milan hinterland, on the historic road that connects Milan Bergamo area, covers an area of about 5 square kilometers and boasts the highest level of excellence in local, cultural, environmental and productive sectors. Vimodrone is characterized by a high presence of prestigious economic activities, craft, industrial, and commercial services. In particular, the availability of public green enjoyed by the citizens is equivalent to 17 square meters per citizen, for a total of 290 thousand square meters. It is located close to motorways that connect to Milan and Venice, and is supplied from the subway that connects the city in 15 minutes to the center of Milan as other major towns such as Cernusco.

The work done

Its recent accession to the Covenant of Mayors, and the special attention paid to energy savings that have characterized in these years, the activity of the technicians and the administrators of the Environmental Office, motivated the Municipality to issue a warning / notice, to national level, aimed, through the work of an advisory committee, to the preparation of the Action Plan for Sustainable Energy. The work of the Commission was participated, as well as CREA Engineering, also by other experts at the national level. We believe we have given, together with the Italian Heat Technology Committee, and other experts at the national level of the Commission, our contribution to the preparation of the Plan which was accepted in full by the European commission. The Action Plan for Sustainable Energy prepared, as you can see from a summary index below reported, is characterized by important elements of practicality, innovation and immediate applicability.
  1. INTRODUCTION AND SUMMARY .............................................................................1
  2. L'INVENTARIO DELLE EMISSIONI.................................................................6
    1. 2.1. EMISSIONS INVENTORY TO 2005 (BASELINE).......................................7
      2.2. EMISSIONS DYNAMIC 2005-2008..........................................................10
      2.3. EMISSIONS SCENARIO TO 2020 ............................................................13
      2.4. MONITORING OF EMISSION INVENTORY .......................15

  3. THE ACTION PLAN .........................................................................................16
    1. 3.1. GENERALÀ.......................................................................................16
      3.2. THE ACTION PLAN TOOLS.................................................16
        3.2.1. PARTECIPATION.......................................................................................17
        3.2.2. PLANNING AREA ........................................................19
        3.2.3. THE BUILDING REGULATION ..........................................................................21
        3.2.4. ENERGY MANAGEMENT SYSTEM ..................................................25
      3.3. ACTIONS............................................................................................26
        3.3.1. BUILDING SECTOR............................................................................................................26
          3.3.1.1. Actions for the existing buildings ...................................26
          3.3.1.2. Actions for the new construction .....................................................30
          3.3.1.3. Actions by solar energy .............................................................31
          3.3.1.4. Actions for the public housing ....................................33
        3.3.2. NETWORK SERVICES...............................................................................................36
          3.3.2.1. Actions by district heating .....................................................36
          3.3.2.2. Actions by the public lighting ............................................40
        3.3.3. TRANSPORT.......................................................................................................42
          3.3.3.1. Completion of S.p. Mirazzano-Cologno Monzese ..........42
          3.3.3.2. Park setting in the central areas ................................43
          3.3.3.3 Extension of the pedestrian cycle ..........................................45
          3.3.3.4. Further extension of the cycle network .......................................46
          3.3.3.5. Parcheggi biciclette e servizio di bike sharing.............................48
          3.3.3.6. Servizio pedibus.................................................................................49
          3.3.3.7. Prolungamento autolinea da c.na burrona a cologno m.se.....49
          3.3.3.8. Servizio car sharing...........................................................................50
          3.3.3.9. Servizio car pooling...........................................................................51
        3.3.4. IL VERDE.............................................................................................................53
          3.3.4.1. Azione con gli alberi..........................................................................53
          3.3.4.2. Azione con l'agricoltura biologica...................................................54
          3.3.4.3. Azione con gli orti sociali..................................................................56
        3.3.5. AZIONE CON LA GESTIONE DEI RIFIUTI......................................................57
        3.3.6. LA GESTIONE SOSTENIBILE DEI SERVIZI PUBBLICI ..............................59
          3.3.6.1. Azione con gli acquisti sostenibili..................................................60
          3.3.6.2. Azione con l'i.c.t..................................................................................61
        3.3.7. AZIONE CONTRO LA POVERTÀ ENERGETICA..........................................62
    2. IL MONITORAGGIO.....................................................................................64
    3. CONCLUSIONI............................................................................................65

    I risultati

    Il lavoro svolto, alla luce dei contenuti e delle idee sviluppate nel corso della predisposizione del piano, permetterà all’ente di programmare e attuare, con razionalità, la propria politica per l’energia sostenibile con importanti risultati in termini di riduzione della spesa e miglioramento della qualità ambientale.